This was said by the head of JSC “NNEGC “Energoatom”, Petro Kotin, on the air of Yedyni Novyny (United News) national telethon.
"We have already repaired most of the power units and returned them to the power grid. Everyone felt the easing of restrictions when two units were connected to the power grid. Two more units left to repair, and we will also connect them before the beginning of the autumn-winter period."
According to the head of the Company, it is possible to shorten the terms of the maintenance campaign, first of all, due to the selfless work of nuclear power professionals. After all, everyone in his place is aware of his own responsibility.
As of today, Energoatom managed to shorten the maintenance campaign period by 25 days. In the future, the Company will work at the same pace, carrying out repairs promptly without loss of quality.
Watch the video for more details about the maintenance campaign at domestic nuclear power plants.
Company news
State of nuclear generation in Ukraine and prospects for cooperation between Energoatom and the EU
30 October 2024
KHAES news
ХАЕС готова до осінньо-зимового періоду
29 October 2024
Company news
russian UAVs have posed a real threat to the safety of the Khmelnytskyi NPP
28 October 2024
Company news
IAEA experts and Energoatom specialists work together to enhance nuclear safety in wartime conditions
28 October 2024